Monday Feb 5: Remaining debris sucked out of NW underfloor ventilation passage and cleared through to the outside vent stones.
Tuesday: Electrician busy with power socket and heater cables; new vestry light fitted.
Wednesday: Oak rail arrived for the SE platform edge. Final loosening of font, ready for moving along the aisle next week.
Electrical fittings and extras agreed with T James Electrical.
Thursday and Friday: PCC decided on design of stackable chair to be used in the new platform area.
New oak rail fitted to edge of SE pew platform pit and joists bedded on damp-proof material.
Location of cables for new power sockets and heaters marked ready for replacing the flooring.
Re-boarding of the floor with recovered tongued and grooved boarding started.
Mobile gantry for moving the font assembled ready for use.
GHP